Longnan Xihe county fire online filing 150 square meter bar decoration need to do those fire procedures?
For this small area, the decoration drawings can be directly sent to the administrative examination and approval center for direct filing, and after the construction is completed, the decoration drawings can be directly filed for acceptance.

Fifteenth the construction unit shall provide the following materials to apply for fire protection design audit:

(a) the construction project fire design audit declaration form;

(2) Legal identity documents such as the business license of the construction unit;

(three) the qualification certificate of the design unit;

(4) Fire protection design documents;

(5) Other materials as prescribed by laws and administrative regulations.

If it is necessary to apply for construction project planning permission according to law, it shall provide a certificate of construction project planning permission; Temporary buildings that need to be approved by the competent department of urban and rural planning according to law, which belong to crowded places, shall provide supporting documents approved by the competent department of urban and rural planning.

Seventeenth fire control institutions of public security organs shall issue written audit opinions within 20 days from the date of accepting the application for fire control design audit. But in accordance with the provisions of the need to organize expert review, expert review time is not included in the audit time.

Twenty-first construction units shall provide the following materials when applying for fire control acceptance:

(a) the construction project fire inspection declaration form;

(two) the project completion acceptance report and the completion drawings of fire control facilities;

(three) the quality certificate of fire protection products;

(four) the certification documents and factory certificates that the building components, building materials and decoration materials that meet the requirements of fire prevention performance meet the national standards or industry standards;

(five) fire facilities inspection documents;

(six) the legal identity certificate and qualification certificate of the construction, project supervision and testing unit;

(seven) the construction unit's business license and other legal identity documents;

(eight) other materials as prescribed by laws and administrative regulations.

Twenty-second fire control institutions of public security organs shall organize fire control acceptance within 20 days from the date of accepting the application for fire control acceptance, and issue opinions on fire control acceptance.