What are the procedures for starting a sand and gravel processing plant?
First of all, you need to apply for three documents, the first is the business license, the second is the mining license, and then there is an EIA approval.

Second, the business license process:

Step one? Approved name

Time: 1-3 working days

Operation: After determining the company type, name, registered capital, shareholders and contribution ratio, you can submit an application for name verification on-site or online at the Industrial and Commercial Bureau.

Results: The name was approved, but it needs to be re-approved if it failed.

The second step is to submit the information.

Time: 5- 15 working days

After approval, confirm the address information, senior management information and business scope, and submit the pre-application online. After the online pre-trial is passed, submit the application materials to the industrial and commercial bureau according to the appointment time.

Results: The notice of establishment registration was received.

The third step is to obtain the certificate.

Time: date of appointment

Operation: Bring the Notice of Approval of Establishment Registration and the original ID card of the manager to the Industrial and Commercial Bureau to obtain the original and duplicate of the business license.

Result: Get the business license.

Third, the EIA approval process;

1. Application and acceptance. According to the Catalogue of Classified Management of Environmental Protection of Construction Projects, the construction unit shall organize the preparation of environmental impact reports for construction projects that may cause significant environmental impact. Apply to the State Environmental Protection Administration in a legal form and submit relevant materials.

The administrative examination and approval hall of the State Environmental Protection Administration accepts the construction project environmental impact report and related materials submitted by the construction unit, conducts verification and decides whether to accept it.

2. Project review. The environmental impact assessment management department of the State Environmental Protection Administration shall review the environmental impact report of the construction project. Where technical assessment is needed, the assessment institution shall organize experts to conduct technical assessment on the environmental impact report, and the assessment institution shall submit the assessment report within 30 working days.

3. Project approval. The Department of Environmental Impact Assessment and Management of the State Environmental Protection Administration puts forward examination and approval suggestions according to the conclusion of the review and evaluation, and reports them to the special meeting of the director of the State Environmental Protection Administration and the executive meeting for deliberation after being countersigned by the relevant departments, and handles the examination and approval documents after being examined and approved.

4. Hearing and information disclosure. The State Environmental Protection Administration publishes the information of accepted construction projects on the government website; Before making an approval decision, publicize the information of the construction project to be approved; After the approval decision is made, the approval result will be made public.

For construction projects that may affect the living environment quality of residents where the project is located and have major differences of opinion, hearings, demonstration meetings and symposiums may be held to solicit opinions from relevant units, experts and the public. Except for construction projects that need to be kept confidential as stipulated by the state.

Extended data

Mining license application conditions

The Department of Land and Resources of Fujian Province recently issued the Notice on Doing a Good Job in the Compilation and Review of Mine Land Reclamation Scheme (hereinafter referred to as the Notice), stipulating that if an applicant applies for new construction, reconstruction or expansion of a mine on August 1 2065438, the applicant shall submit a land reclamation scheme that meets the requirements;

201July 3, 41The mining right holder who has obtained the mining license a few days ago shall prepare a land reclamation plan. If it is not prepared, it shall complete the supplementary preparation and review of the plan within one year and report it to the original issuing authority for the record.

The Notice stipulates that if surface land is destroyed by open-pit mining, surface land collapses by underground mining, mining stripping, waste rock, slag, fly ash and other solid wastes occupy land, the applicant shall go through the formalities for examination and approval of mining rights.

According to the requirements of the Ministry of Land and Resources, a land reclamation plan shall be prepared by a unit with the qualification of land remediation design and submitted to the land and resources department of the county (city) where the mine is located for review.