What is the time sequence of infilled wall masonry, formwork, steel bar installation and concrete pouring in civil engineering?
Cast-in-place concrete walls and columns shall be reinforced first, the formwork shall be closed after concealed acceptance, and the pouring order shall be issued by the supervisor for concrete mixing;

Cast-in-place concrete beam and slab should be closed before reinforcement, and concealed acceptance should be carried out, and the pouring order should be issued by the supervisor for concrete mixing;

After the formwork removal of the frame, the infilled wall can be laid according to the plan of the project department during the period from the main body construction to the basic end.