List the general provisions of Chapter 100.
Detail number, subtitle name, unit quantity, unit price and price
10 1- 1 insurance premium
-a provide the total amount of all risks of construction projects specified in the contract terms.
-b the total amount of third-party liability insurance provided according to the terms of the contract.
102- 1 total completion document
102-2 Total construction environmental protection fee
103- 1 Total amount of temporary road construction, maintenance and demolition (including original road maintenance fee)
Temporary works103-2m2
103-3 temporary power supply facilities m2
-Total installation and dismantling of facilities
-b facility maintenance month
103-4 Total amount of provision, maintenance and dismantling of telecommunication facilities
103-5 total water supply and sewage facilities
104- 1 total amount of contractor's site construction
List Chapter 65438 +000 Total RMB
schedule of quantities
Chapter 200 Subgrade List
Detail number, subtitle name, unit quantity, unit price and price
202- 1 Cleaning and excavation
-Clean up the site m2
-b cutting down trees
-c uprooted.
202-2 Excavation of Old Pavement m2
-cement concrete pavement m2
-b asphalt concrete pavement m2
-c macadam pavement m2
202-3 Structural Demolition
-A reinforced concrete structure m3
-b concrete structure m3
-Brick, stone and other masonry structures m3
203- 1 subgrade excavation
-one excavation m3
-b rock excavation m3
-Excavate materials (including silt) not suitable for m3.
203-2 River change, canal change and road change during excavation.
-Earthwork quantity m3 for one excavation
-b excavation m3
-c ……
204- 1 subgrade filling (including compaction before filling)
-Replacing soil m3
-b using earthwork m3
-c Use cubic meters of stone
-d Fill m3 with earth-rock mixture.
-e borrow soil to fill m3.
-f fly ash embankment m3
-m3 backfilling of abutment of G structure
204-2 Changing roads, rivers and canals.
-a using earthwork m3
schedule of quantities
Chapter 200 Subgrade List
Detail number, subtitle name, unit quantity, unit price and price
-b Use cubic meters of stone.
-c borrow soil to fill m3.
205- 1 Soft soil foundation treatment
-Riprap and silt squeezing m3
-b sand cushion and gravel cushion m3
-c lime-soil cushion m3
-d preloading and overload preloading m3
-e bagged sand drain m
-f plastic drain plate m
-gram DJM pile m
-h gravel pile m
-i sand pile m
-j geotextile m2
205-2 Landslide Treatment m3
205-3 Cave Backfilling m3
205-4 expansive soil treatment
-Thickness ... square millimeters
205-5 Loess Treatment
-A m3 sinkhole
-b collapsible loess m2
205-6 Saline Soil Treatment
-Thickness ... square millimeters
207- 1 ...M mortar rubble ditch
207-2 ...M-class mortar rubble drainage ditch
207-3 ...M-class mortar rubble intercepting ditch
207-4 ... Mortar rubble rapids m3.
207-5 subgrade blind ditch, ... x ... meters (abbreviation of meter))
207-6 Trenching and Laying of Upstream and Downstream Culverts M
208- 1 Planting grass and paving turf m2
schedule of quantities
Chapter 200 Subgrade List
Detail number, subtitle name, unit quantity, unit price and price
Grade 208-2 ... Masonry slope protection
-An arched slope protection m3
-b grille slope protection m3
208-3 Precast Concrete Block Slope Protection
-A precast hollow brick slope protection ㎡.
-b arch skeleton slope protection ㎡.
-c grille slope protection ㎡.
208-4 facing wall
[Ancient or Latin modern names of animals and plants] ... mortar brick (block stone) m3.
-Grade B ... Concrete m3
-c gravel (crushed stone) cushion m3
209- 1 retaining wall
-Grade A ... Mortar brick (block) stone m3
-Grade B ... Concrete m3
-c gravel (crushed stone) cushion m3
-d steel bar
2 10- 1 anchor retaining wall
-concrete column (C…) m3
-b concrete baffle (C…) m3
-c steel bar
-d bolt
2 1 1- 1 reinforced earth retaining wall
-Class A … Mortar rubble foundation m3
-Class B ... Concrete foundation m3
-Class C ... concrete cap stone m3
-D ... concrete wallboard m3
-Class E ... Reinforced concrete belt m3
-f polypropylene geotextile
2 12- 1 geogrid shotcrete slope protection, thickness … mm
schedule of quantities
Chapter 200 Subgrade List
Detail number, subtitle name, unit quantity, unit price and price
-Thick ... sprayed concrete for slope protection.
-b barbed wire
-c geogrid ㎡.
-d anchor m
2 12-2 net shotcrete slope protection (full slope)
-Thick ... mm sprayed concrete to protect the slope m2.
-b steel mesh
-c barbed wire
-3D geogrid m2
-e anchor m
2 12-3 slope protection
-sprayed concrete (thickness … mm) m2
-b sprayed cement mortar (thickness … mm) m2
2 13- 1 prestressed anchor cable (steel strand specification) m
2 13-2 concrete anchor plate (C…) m3
2 14- 1 concrete anti-slide pile
-a …m×…m, … Grade concrete anti-slide pile M
-b …m×…m, … Grade concrete anti-slide pile M
-One steel bar (ribbed steel bar)
2 15- 1 grade ... Mortar rubble river bed paving m3.
215-2 ... Class Ⅱ masonry dam m3
2 15-3 ... Class I masonry rockfill dam m3
2 15-4 ... Graded slurry masonry dam m3
2 15-5 ... Mortar rubble cone slope m3
List Chapter 200 Total RMB.
schedule of quantities
Chapter 300 Pavement Listing
Detail number, subtitle name, unit quantity, unit price and price
302- 1 macadam cushion
-Thickness ... square millimeters
302-2 gravel cushion
-Thickness ... square millimeters
303- 1 lime stabilized soil subbase
-Thickness ... square millimeters
304- 1 cement stabilized soil subbase
-Thickness ... square millimeters
304-2 Cement Stabilized Soil Base
-Thickness ... square millimeters
305- 1 lime fly ash stabilized soil subbase
-Thickness ... square millimeters
305-2 lime industrial waste residue stabilized soil base
-Thickness ... square millimeters
306- 1 graded macadam subbase
-Thickness ... square millimeters
306-2 graded macadam base
-Thickness ... square millimeters
306-3 graded gravel subbase
-Thickness ... square millimeters
307- 1 primer m2
307-2 adhesive layer m2
307-3 seal coat m2
308- 1 fine grained asphalt concrete
-Thickness ... square millimeters
-b thickness ... square millimeters
308-2 medium-grained asphalt concrete
-Thickness ... square millimeters
-b thickness ... square millimeters
schedule of quantities
Chapter 300 Pavement Listing
Detail number, subtitle name, unit quantity, unit price and price
308-3 coarse-grained asphalt concrete
-Thickness ... square millimeters
-b thickness ... square millimeters
309- 1 asphalt surface treatment
-Thickness ... square millimeters
-b thickness ... square millimeters
3 10- 1 modified asphalt mixture
-Thickness ... square millimeters
-b thickness ... square millimeters
3 1 1- 1 cement concrete panel
-a thickness …mm (concrete flexural tensile strength MPa) m2
-b thickness …mm (concrete flexural tensile strength MPa) m2
3 12- 1 shoulder m3
3 12-2 central reserve fill m3
3 12-3 cast-in-place concrete reinforced earth shoulder (thickness …mm) m
3 12-4 earth shoulder reinforced by precast concrete block (thickness …mm) m
3 12-5 concrete precast block kerb m
3 13- 1 drain pipe
-PVC-U tube φ ... φ ... mm
-b Cast iron pipe φ ... φ ... mm
-Concrete pipe φ c ... φc...φ… mm
3 13-2 meter of longitudinal rainwater ditch (pipe)
Class 3 13-3 … concrete sump seat
3 13-4 seepage ditch in central separation zone …mm×…mm×…mm m
3 13-5 asphalt felt waterproof layer m2
3 13-6 shoulder drain
-concrete shoulder drain pipe m
-b gravel cushion m3
-c geotextile m2
3 13-7 water retaining belt
-asphalt concrete water retaining belt m
-b cement concrete waterstop m
List Chapter 300 Total RMB
List Chapter 400 Bridges and Culverts
DetailNo. Detail Name Unit Quantity Unit Price and Price
4 13-4 Precast Concrete Block with Mortar
-One ... cubic meter
4 15- 1 asphalt concrete bridge deck pavement (thickness …mm) m2
4 15-2 cement concrete bridge deck pavement (… grade, thickness …mm) m2
4 15-3 waterproof layer (thickness …mm) m2
4 16- 1 rectangular plate rubber bearing
4 16-2 circular rubber bearing
4 16-3 spherical cap disc rubber bearing
4 16-4 washbasin bracket
4 16-5 spherical bearing
4 17- 1 rubber expansion device m
4 17-2 modular telescopic device m
4 17-3 filler expansion device m
4 19- 1 single-hole reinforced concrete circular pipe culvert, φ … mm
4 19-2 double-hole reinforced concrete circular tube culvert, φ … mm
Grade 4 19-3 … reinforced concrete circular inverted siphon, φ … mm …
420- 1 reinforced concrete slab culvert, … m× … m m.
420-2 reinforced concrete box culvert, … m× m.
42 1- 1 arch culvert … m××× m m.
Chapter 400th List of Total Renminbi
schedule of quantities
Chapter 500th Tunnel List
Item names of detail numbers are unit quantity, unit price and price.
502- 1 tunnel excavation
-One cubic meter of earthwork
-b m3 stonework
-c abandon the party transport m3? kilometre (km)
502-2 Waterproofing and Drainage
-Grade A ... Mortar rubble intercepting ditch m3
-b nonwoven m2
…
502-3 Portal Slope Protection
-Grade A ... Mortar macadam m3
-Class B ... shotcrete m3
-c planting turf m2
…
East Gate Building 502-4
-Grade A ... Concrete m3
-B ... Mortar coarse aggregate stone (block stone) m3
…
502-5 Open Tunnel Lining
-Grade A ... Concrete m3
-Grade B round steel (Grade I) kg
-c ribbed steel bar (HRB335) kg
…
502-6 Shading shed (board)
-Grade A ... Concrete m3
-Grade B round steel (Grade I) kg
-c ribbed steel bar (HRB335) kg
…
502-7 Roof Backfilling
-backfill earthwork m3 at one time.
503- 1 Tunnel excavation
schedule of quantities
Chapter 500th Tunnel List
Detail number, subtitle name, unit quantity, unit price and price
-One cubic meter of earthwork
-b m3 stonework
-c abandon the party transport m3? kilogram
503-2 Advanced Support
-One anchor (specification) m
-b small steel bar (specification) m
-c pipe shed (specification) m
-d grouting small catheter (specification) m
-e-beam (specification) kg
……
503-3 shotcrete and bolt support
-Class A ... sprayed steel fiber concrete m3
-Class B ... shotcrete m3
-c grouting anchor (specification) m
-d anchor (specification) m
-Kilogram of steel mesh
503-4 Wood m3
504- 1 tunnel lining
-Grade A ... Concrete m3
-a ... waterproof concrete m3
-C ... Mortar coarse aggregate stone (block stone) m3
-d round steel bar (Grade I) kg
-e ribbed steel bar (HRB335) kg
Class 504-2 ... Inverted arch, subgrade concrete m3.
504-3 ... Concrete m3 of slope side trench and cable trench
504-4 Portal (Specification)
504-5 hole pavement
-Grade A concrete (thickness …) m2
schedule of quantities
Chapter 500th Tunnel List
Detail number, subtitle name, unit quantity, unit price and price
-A round bar (level 1)
-c ribbed steel bar (HRB335)
505- 1 Waterproofing and drainage
Waterproof board m2
-b nonwoven m2
-c waterstop m
-d water stop m
-e pressure injection cement sodium silicate slurry t
-f pressure grouting cement slurry t
-g grouting borehole m
-h Drainage pipe φ ... φ ... mm
……
506- 1 tunnel fire retardant coating
-Spray fire retardant coating m2
506-2 Tunnel Decoration Project
-One m2 tile
-b spraying special paint m2 for concrete
508- 1 monitoring measurement
-Total amount of required projects (project name)
-b Total amount of the selected project (project name)
509- 1 total geological forecast (detection means)
List the total RMB in Chapter 500.
schedule of quantities
List Chapter 600 Safety Facilities and Embedded Pipes
Detail number, subtitle name, unit quantity, unit price and price
602- 1 grade ... concrete guardrail m
602-2 Single-sided Corrugated Beam Steel Guardrail M
602-3 double-sided corrugated beam steel guardrail M
602-4 movable steel guardrail
Head end of 602-5 corrugated beam steel guardrail
-Separate round-headed end pieces
-b, separated ground anchor type end.
-c combined round end
Class 602-6 ... Concrete foundation m3
603- 1 steel wire fence m
603-2 barbed wire m
603-3 wire mesh isolation grid m
603-4 Welded Mesh Isolation Grid M
603-5 Bridge Protection Network M
603-6 Reinforced Concrete Column Root
Root of 603-7 steel column
604- 1 single column traffic sign
604-2 double-column traffic sign
604-3 three-pillar traffic sign
604-4 Portal Traffic Signs
604-5 single cantilever traffic sign
604-6 Double Cantilever Traffic Sign
604-7 Hanging traffic signs
604-8 milestones
604-9 Highway Boundary Piles
604-10m pile
605- 1 hot melt paint pavement marking
-1 marker line m2
Mark m2 of -b 2
605-2 solvent-based normal temperature paint pavement marking
schedule of quantities
List Chapter 600 Safety Facilities and Embedded Pipes
Detail number, subtitle name, unit quantity, unit price and price
-1 marker line m2
Mark m2 of -b 2
605-3 solvent-based heating paint pavement marking
-1 marker line m2
Mark m2 of -b 2
605-4 Prominent Road Signs
605-5 profiler
-a-pillar delineator
-b additional plotter
605-6 facade sign
606- 1 anti-glare board m
606-2 anti-glare net m
607- 1 man (hand) hole
607-2 emergency telephone platform
607-3 pipeline project
-a Laying … Hole φ … Plastic pipe (steel pipe) pipeline M
-b Laying … hole φ … plastic pipe (steel pipe) pipeline M
-c Laying … hole φ … plastic pipe (steel pipe) pipeline M
-d Laying … hole φ … plastic pipe (steel pipe) m
-e Manufacture and installation of bridge boxes (including boxes with joints at both ends) m
608- 1 toll station
-A toll booth
-b toll booth for two people
608-2 upper charge limit m2
608-3 Toll Island
-One-way toll island
-b two-way toll island
608-4 underground passage (height× width) m
608-5 embedded pipeline
-a (pipe specification) m
-b (pipe specification) m
schedule of quantities
List Chapter 600 Safety Facilities and Embedded Pipes
DetailNo. Detail Name Unit Quantity Unit Price and Price
608-6 Pipeline Installation
-a (pipe specification) m
-b (pipe specification) m
Chapter 600th Total RMB List
schedule of quantities
Chapter 700th List of Greening and Environmental Protection
Detail number, subtitle name, unit quantity, unit price and price
702- 1 excavation and topsoil laying
-embankment slope m3
-b median m3
-c service area m3
……
702-3 Topsoil for paving and utilization
-embankment slope m3
-b median m3
-c service area m3
……
703- 1 sowing grass seeds
-Embankment gradient m2
-b service area m2
……
703-2 Planting Turf
-Embankment gradient m2
-b service area m2
……
703-3 Greenland sprinkler irrigation pipeline M
-embankment slope m
-b service area m
……
704- 1 artificial tree planting
-service area tree
……
704-2 Artificial Shrub Planting
-Intermediate tree
-b service area tree
……
704-3 Artificial Planting of Climbing Plants
-Embankment slope tree
-b service area tree
……
706- 1 anechoic panel sound barrier m
706-2 Sound Absorbing Brick Sound Barrier m3
706-3 Brick Wall Sound Barrier m3