(1) Set out the axis pile and pile position pile, and lead them out with reference line, and set out the axis pile and pile position pile near the piling area.
(2) Test piles to determine the penetration and hammering number of the pile loosening machine.
(3) According to the test results, loosen the pile according to the test requirements.
(4) In accordance with relevant regulations, check and accept pine stakes.