The order of template removal is announced!
Template removal is an important link in building construction, and it is also a technical activity. Correct demolition sequence and method can not only improve construction efficiency, but also ensure construction safety. This paper will reveal the order and matters needing attention of formwork removal for everyone, and help them to carry out construction better.

Small principle of demoulding

The small principle of formwork removal includes the following points: first remove the back brace, first remove the non-load-bearing structure, then remove the load-bearing structure, and from top to bottom, first remove the side structure, then remove the vertical structure. These principles can help constructors to remove the formwork better.

Demolition of complex formwork

For complicated formwork removal, a special formwork removal construction scheme must be formulated and approved before formwork removal operation can be carried out.

General demolition sequence

The general demolition sequence is foundation → formwork → plate support → plate formwork → beam side formwork → beam support → beam bottom formwork → wall formwork. This sequence can ensure the smooth progress of the construction.

Other component templates

Used for formwork of other components, such as stairs, balconies, overhangs, ring beams, constructional columns, etc. , must first remove the support, and then remove the template. This can ensure the construction safety.

Matters needing attention in dismantling formwork

Precautions for formwork removal include specialist command, avoiding cross-construction, gentle removal, temporary support and block-by-block removal. These preventive measures can ensure the safe and smooth construction.