Current location - Plastic Surgery and Aesthetics Network - Plastic surgery and beauty - What are the preparations for the construction of the subbase of the gap-filling macadam cushion?
What are the preparations for the construction of the subbase of the gap-filling macadam cushion?
Next, Zhong Da Consulting will introduce in detail the preparation for the construction of the sub-base of the gap-filling macadam cushion for your reference.

Prepare the construction plan

Prepare the construction plan, submit the commencement report and submit it to the supervisor for approval.

technical disclosure

Be familiar with construction drawings and organize technical disclosure.

Covering construction

Overlay facilities.

Material sampling inspection test

Materials shall be sampled and submitted for testing, and the test results shall be submitted to the supervisor for approval.

Subgrade treatment

Subgrade cleaning, shaping, cleaning, watering and rolling; Scroll. Then the subgrade is comprehensively tested, especially the compactness, deflection value and elevation of subgrade. Seriously deal with the place that does not meet the design requirements until it meets the requirements.

Re-measure subgrade

Re-measure the width, height, longitudinal slope, transverse slope and superelevation transverse slope of subgrade.

Subgrade surface treatment

Deal with the place where there are loose soft bullets on the subgrade surface, especially soft bullets, dig out the soft bullets and backfill them with lime soil or gravel soil.

Prevent water accumulation in road grooves

In the trough section, drainage ditches or gravel blind ditches should be alternately excavated at regular intervals (5 ~ 10m) on both sides of the shoulder to prevent water accumulation in the road trough.