What is the situation of group purchase construction in Fuzhou East New District?
It's good. This month, about 33 19㎡ of the above-ground main structure, about 870㎡ of the basement main body, about 43% of the masonry works of plots A and B, and about 35% of the internal and external painting works were completed. Up to now, the total progress: the above-ground main structure of plots A and B is about113300m2, accounting for 9 1.5%, the main basement project is about 37,500m2, accounting for 94.7%, the masonry project of plots A and B is 68%, and the internal and external painting project is 55%.