Environmental Protection Acceptance Document of Xianyang Northwest Medical Equipment (Group) Co., Ltd.
Technical transformation and factory expansion project of Xianyang Northwest Medical Equipment (Group) Co., Ltd.

Publicity materials for completion acceptance

I. Basic information of the project:

At present, Northwest Medical is the only enterprise with mature dental comprehensive treatment machine and dental mobile phone manufacturing technology in China. Technical renovation and expansion were carried out on the original land, with a total investment of 76,652,500 yuan, a new building area of 22,500 square meters, a reconstructed area of 1.55 million square meters, and new production lines for dental comprehensive treatment machines, dental mobile phones, digital imaging products and minimally invasive equipment.

Construction unit: Xianyang Northwest Medical Equipment Co., Ltd.

Construction site: Xianyang Northwest Medical Equipment Co., Ltd.

Project investment: The actual total investment of the project is 70.276 million yuan, including 845,000 yuan for environmental protection.

Project construction: The project started in 2009 and was completed in February 20 10. The environmental protection acceptance monitoring report was provided in February 2011year 10.

Project Approval Unit: Xianyang Environmental Protection Bureau

Acceptance monitoring units: Xianyang Environmental Monitoring Station and Qingdao Jingcheng Testing Technology Co., Ltd. ..

Second, implement environmental protection.

During the project construction, the construction unit can attach importance to environmental protection, and the project construction can fulfill all the declaration and approval procedures in accordance with the relevant state regulations on environmental protection management of construction projects. In the construction of the project, the environmental management system and environmental management system can be established and improved according to the requirements of the "three simultaneities" system, and the operating load reaches more than 75% at the time of acceptance.

Three. Acceptance monitoring results

1. Wastewater: The suspended solids, PH, copper and zinc in the treated electroplating wastewater meet the secondary standard in Table 4 of GB8978- 1996, and the hexavalent chromium meets the standard in Table 4 of GB8978- 1996.

2. Noise: * * Four monitoring points are arranged in total. Due to the influence of traffic, the daytime noise at the boundary of 1 and 2 monitoring points exceeds the second-class standard requirements of GB 12348—2008 Environmental Noise Emission Standard for Industrial Enterprises; The daytime noise at the boundary of No.3 and No.4 monitoring points meets the secondary standard requirements of GB 12348—2008 Emission Standard for Environmental Noise at the Boundary of Industrial Enterprises.

3. Exhaust gas: Qingdao Jingcheng Testing Technology Co., Ltd. was entrusted to monitor the exhaust gas. The concentration and emission rate of non-methane total hydrocarbons, benzene, toluene, xylene and particulate matter at the exhaust gas outlet all reached GB 16297- 1996 Comprehensive Emission Standard for Air Pollutants.

4. Solid waste: the metal waste generated by the project is collected and sold, and the sludge generated by the sewage treatment station of the electroplating workshop is dehydrated and handed over to a qualified unit for hazardous waste treatment; Domestic garbage is collected by classification and handed over to the local sanitation department for treatment.

Four. Acceptance conclusion

The project meets the requirements of the environmental impact report form and approval, and takes corresponding environmental protection measures. Major pollutants discharged up to standard, pollution-free disputes and environmental violations during trial production. The main pollution indicators meet the environmental protection acceptance conditions for completion, and it is agreed to pass the environmental protection acceptance for completion.