Article 1 Self-inspection Report on Infrastructure Project Construction
According to the spirit of the instructions of the leading group for poverty alleviation and development, under the leadership of the district party committee and the district government, and with the efforts of the member bureaus of our district infrastructure group, the poverty alleviation infrastructure projects in our district are being carried out rapidly and orderly. The infrastructure construction in our district is now reported as follows: 1. Work objectives.
Focusing on the overall goal of getting rid of poverty, at this stage, our district plans to implement village roads in 20xx, with a total mileage of 42.798 kilometers; There are 274 dangerous houses, 3 village-level public service facilities, drinking water consolidation and upgrading project 1 seat, and 2 small bridges. The planned investment is 24.62 million yuan.
Second, complete the work at this stage.
1, village road construction. At present, there are: 33 roads (the second batch of district transportation bureaus plans to add 5) and 42.798 kilometers of roads; Two small bridges. Total investment16.78 million yuan. Twenty-nine roads and two small bridges have been started. Completed 27 articles and 2 small bridges; Completed 267 1 km with an investment of 1. 1.356 million yuan. Accounting for 68% of the total investment. In which: District Poverty Alleviation Office 1 1 13.8km, with an investment of 4.42 million yuan; Construction has all started, with 9 12 1 km completed, with an investment of 3.978 million yuan. Construction of District Transportation Bureau 1 1 (the second batch of six plans)15.698km, with an investment of 7.85 million yuan; Construction has all started, with 9 sections of 7.62 kilometers completed and an investment of 4.42 million yuan. The Reservoir Immigration Bureau plans to integrate project funds of 3.3 million yuan, build Tunji Highway 7 ***9.424 kilometers, start construction of three highways 3. 15 kilometers, and complete the investment of 1 10.3 million yuan. The Administration for Religious Affairs plans to integrate the project funds of 1, 4 1, 000, and build five roads with a length of 3.84 kilometers, which have all been completed.
2. Dangerous building renovation project. The District Construction Bureau plans to renovate 274 dangerous houses (poor households with established files) with an investment of 7.26 million yuan. By August 25th, we had started 107 sets and completed 56 sets. At present, the focus of the work is the ongoing verification work at the township level, and the housing situation of the reconstruction targets is checked house by house, and the list of reconstruction households is determined.
3. Construction of village-level public service facilities. The District Cultural and Sports Bureau raised funds to build three village-level service centers with an investment of 900,000 yuan. Three village-level service facilities construction projects, the main construction content is to complete the "six ones" construction, that is, the comprehensive building, basketball court, stage, publicity column (wall), art team and sports team with a construction area of not less than 160m2. At present, all three projects have started construction, among which the main frame construction of three comprehensive buildings has been completed and the wall construction is under way.
4, rural drinking water safety consolidation and upgrading project. 1 project. It is planned to implement the rural drinking water safety consolidation and upgrading project in the closed village of Donglong Town to improve the drinking water conditions of the people in the project area. This project is in the charge of the District Water Conservancy Bureau. The planned investment is 250,000 yuan, which has been implemented1940,000 yuan. Main construction contents: 530m3/d water supply, 1 new 200m3 high-level pool, disinfection equipment and ancillary buildings. All the projects have been completed.
Third, the main work measures
1. The district party committee and district government attach great importance to the project construction. District Party committees and district governments hold poverty alleviation work meetings regularly every week to listen to the report on the project construction and take effective measures to solve the problems and difficulties encountered in the project construction process in time.
2, the relevant departments should seriously organize the implementation. The main leaders of the department personally grasp, in charge of the specific leadership, and implement it to specific staff. The main leaders went deep into the project construction site to coordinate and solve problems and difficulties in time to ensure the smooth progress of the project construction.
3, the financial evaluation department closely cooperate, give priority to the budget review of poverty alleviation infrastructure projects.
4. Strengthen supervision and inspection. The lead unit of the infrastructure task force regularly and irregularly supervises and inspects the project construction of relevant departments, promptly urges the departments to make rectification when problems are found, and does everything possible to speed up the project construction progress.
Four, the existing problems and problems that need to be solved in coordination.
1. Of the seven projects of the Immigration Bureau, only three have received funds, and the other four have not yet received funds. It is understood that the four projects included in the plan may not necessarily get more funds. If the funds are really not enough, it will affect the completion of the task throughout the year. Our team has communicated with the Immigration Bureau and asked them to contact the higher authorities as soon as possible to determine the implementation of funds for these four roads as soon as possible so that we can take countermeasures.
2. The renovation of dilapidated buildings is progressing slowly, and the number of households that have started construction only accounts for 40% of the total. The main reason is that the implementation plan of dangerous houses at higher levels has not been decided, and some poor households have not raised funds by themselves.
3. Please ask the district committee and government to coordinate whether the four-way project that the Immigration Bureau has not allocated is cancelled.
4. Some poor households have no self-raised funds, and the renovation of dilapidated houses cannot be implemented. How to solve the problem of self-financing
Verb (abbreviation for verb) Next work plan
1, do a good job of supervision, inspection and completion acceptance of the project to ensure that the project completion acceptance is completed on time.
2. For projects with unfunded funds, strengthen coordination and communication with relevant departments, implement project construction funds as soon as possible, and strive to start construction as soon as possible.
3, the dangerous building renovation work as the focus, earnestly, to ensure that the construction task is completed on time.
4. Accelerate the disbursement of project funds, complete one project, accept one project and settle one project, and complete the disbursement of funds on time.
Article 2 Self-inspection report on infrastructure project construction
Since 20XX, our bureau has actively carried out the construction of comprehensive agricultural projects in villages and towns in accordance with the requirements of the Implementation Plan of Comprehensive Rural Projects in Counties in 20XX. The self-inspection of the work carried out from June 5 to April is now reported as follows: 1. Work development.
(1) Strengthen organizational leadership. A leading group for the construction of 20XX township agricultural comprehensive projects of county agricultural bureau was set up, with the party secretary and director of the bureau as the team leader, other team members as the deputy team leader (the deputy director in charge of the project is the deputy team leader), and the heads of relevant stock stations and offices as members. There is an office under the leading group, which is located in the financial planning unit of the bureau, and the chief of the financial planning unit concurrently serves as the director of the office, specifically responsible for coordinating the daily work of township comprehensive agricultural projects. Hold relevant working meetings for many times, arrange and deploy 22 projects in charge of our bureau, decompose each project plan into responsible units and responsible persons, effectively strengthen the organization and leadership of project construction, and put the construction of township agricultural comprehensive projects on the important agenda.
(2) do a good job in the preliminary work. Actively contact and dock with the villages and towns of the project, and do a good job in the preparatory work for the project. All 22 projects have completed the project survey, design and budget. By the end of April, special funds of 1 1.97 million yuan had been arranged for 22 projects, and another 12 comprehensive agricultural projects in villages and towns were being planned.
(3) Strengthen project management. Implement the systems of project bidding management, safety management, fund management and project quality management. Strict implementation of "project design, financial evaluation, bidding, construction, audit settlement, reimbursement" and other project construction related procedures; Strengthen the tracking audit of the use of project funds to ensure the safe and efficient use of funds. There were no incidents 1 such as work stoppage, theft and group petition. And report the project progress and major situation in time as required.
Second, the main problems and the next step
(1) Main problems. First, the long work cycle in the early stage of the project has affected the approval speed of some projects; Second, the slow arrival of project funds has affected the construction progress of some projects; Third, agricultural projects are seasonal, which has a great impact on the project construction progress.
(2) Next step. The first is to grasp the progress. Further intensify the coordination service, concentrate on solving the difficulties and problems existing in the project implementation process, ensure the safe construction of the project according to the expected schedule, and see results as soon as possible. The second is to grasp management. Further strengthen project supervision and inspection, strengthen project fund management, and improve the quality and efficiency of project construction. The third is to grasp the environment. Efforts should be made to enhance the consciousness of all sectors of society to care for and support the construction of township agricultural comprehensive projects and create a better environment for project construction.
Article 3 Self-inspection Report on Infrastructure Project Construction
I. Overview There are 24 administrative villages in XX Town, 159 villagers' groups with 34,000 people. It is a key town in Henan Province, a top 30 town with comprehensive strength in * City, and the location of six key industrial parks in xinzheng city-a pharmaceutical and chemical industry cluster.
Over the past few years, XX Town has given full play to the advantages of transportation location, pharmaceutical and chemical industry group and superhard materials group, insisted on starting small, winning with more, highlighting the leader, forming a cluster, and striving to build Xinzheng "new district", and established the strategic goal of building XX into a "northern pharmaceutical and chemical industry cluster". There are more than 20 industrial enterprises/kloc-0, with a total investment of nearly 2 billion yuan. Among them, there are 8 pharmaceutical manufacturers headed by Ling Rui Pharmaceutical Co., Ltd. and Henan Lingyou Pharmaceutical Co., Ltd., which mainly produce chemicals, Chinese patent medicines, biological medicines and raw materials. There are also various injections, tablets and capsules. The annual output of water injection alone is nearly 3 billion, which is one of the main production bases of water injection in China. The development of pharmaceutical industry has also led to the rise of supporting industries, such as oxygen production, ampoule manufacturing, printing and packaging, foam products and so on. Now, XX has become the hometown of Xinzheng's development environment and product structure, realizing the synchronous and coordinated development of economy and society.
Second, infrastructure construction
In *, the town covered an area of 4.6 square kilometers with a population of 27,000. The town's GDP reached 760 million yuan, the fiscal revenue was 8.26 million yuan, the annual disposable income was 6 1 10 yuan, the per capita green area 10 square meter, the per capita road pavement area 16 square meter, the green coverage rate reached 34%, the telephone penetration rate reached 92%, and the tap water penetration rate reached/kloc-.
(1) general situation of engineering infrastructure
However, the township's infrastructure can no longer meet the needs of economic development, in order to further promote the sustained and rapid development of XX economy. The town party committee and government put forward the strategy of establishing the town by industry and strengthening the town by industry, adjusted the overall planning in time, broadened the framework of the town and drew the blueprint for development. After demonstration, the investment is 265,438+600,000 yuan to build Hua Fu Avenue with high standards. The project is 685 meters long and 30 meters wide. The pavement is poured with concrete, and street lamps on both sides are under construction. The completion of this road provides great convenience for employees and vehicles of Hua Fu Iron and Steel Co., Ltd. and Chen Zhuang Substation to travel; Invested 96,000 yuan to drill a deep well for Hetaoyuan Village Group, which solved the draught problem of nearly 800 people. Invested 850,000 yuan to renovate or build new drainage pipelines in the township, which solved the problem of poor drainage of roads in the township; Invested in the maintenance of public toilets and garbage collection points in the township, one in Oujiang Garden and one in Sinking Square, and built three garbage transfer stations.
Social infrastructure
At present, there are 9 schools of all kinds, covering kindergarten, primary school, junior high school, senior high school and university education, forming a complete cultural and educational system; There is a health center, which is the joint hospital of xinzheng city People's Hospital; New nursing homes are also under construction; Rural bus 102 goes directly to Xinzheng city; The total installed telephone number is113.28 million, the mobile phone station covers the whole town, and the PHS station covers the whole town. There is a waterworks in the township with a daily water supply capacity of 1 1,000 cubic meters, and the tap water penetration rate in the township reaches 1 1,000%. At present, there are 2 TV turntables, and 45 sets of programs have been broadcast. There are 5 1 household 153 people in the township who are included in the minimum living allowance, and 40 yuan enjoys-160 yuan/month.
This town looks like a village.
In recent years, the town government has reformed Zheng Xin Highway, 107 National Highway, XX Avenue and Yucai Road, with emphasis on greening project, lighting project, house reconstruction along the street and road hardening project. Shops along the street implemented the responsibility system, cleared weeds and sundries, planted trees and afforested, completed the urban greening construction project with high standards, and realized "one road with one color" and "one street with one scene". The appearance of cities and towns has improved significantly, and the quality of village construction has improved significantly.
Third, there are problems.
Because of the early development of XX town, although the infrastructure is complete, but because of its close proximity to the national highway 107, there are many transit vehicles, the road aging is more serious, and there are dust and white garbage pollution.
Fourth, the rectification measures
1, strive for loans from national banks and strengthen the transformation of township infrastructure.
2. Strengthen the greening on both sides of the road to alleviate dust pollution.
3. Strengthen the treatment of white garbage along the national highway.