1, measure the defense line;
2. Excavation of foundation pit;
3, copy flat;
4, do the concrete foundation cushion;
5. Tie steel bars, install templates and pour concrete;
6, measuring unreeling (axis, column positioning);
7, column steel binding, template installation, concrete pouring;
8, beam, plate steel binding, template installation, concrete pouring in turn, until the cap.
9. Masonry construction, plastering of internal and external walls, installation of door and window frames, roof waterproofing, external wall facing construction, etc. , can be interspersed with construction after the completion of the main structure.