How to calculate the earthwork volume of foundation pit and foundation trench
Understand the common earthwork in civil construction, including: site leveling; Excavation of foundation pit, foundation trench and pipe trench. Calculation and distribution of earthwork: master the calculation of earthwork, including earthwork of foundation pit and foundation trench.

Calculated according to the following provisions:

L, artificial leveling site refers to the excavation, filling and leveling within 30cm of the construction site. Digging and filling, when the thickness exceeds 30cm, shall be calculated separately according to the vertical arrangement of earthwork balance on site.

2. The engineering quantity of the leveling site is 2m on each side of the external wall of the building, calculated in square meters.

3. The original soil of the construction site shall be rolled in square meters, and the filled soil shall be rolled in cubic meters according to the thickness of the filled soil shown in the figure.

Extended data:

Earthwork completion acceptance data:

Earthwork is divided into several properties, one is site leveling, and the other is rock cutting. At present, we don't have a special filing catalogue for these majors. When filing, the documents can be classified according to the construction standards, approved by the quality acceptance department, and filed after meeting the construction and acceptance specifications.

After the completion of the earthwork project, it has nothing to do with the main body. The earthwork project and the project invested by the enterprise can be put on record by the construction unit. Government investment shall be filed and handed over to the municipal urban construction archives. Quantity measurement of earthwork quota.

Baidu encyclopedia-earthwork volume