Because the total number is the same, so 600*20= 15*X, X=800, so 800 sets are actually produced every day.
(2) If the construction period is reduced by 2 days, it will be completed in 10 day.
Let's have x people, because the total amount remains the same,
So 25* 12= 10X, X=30, so 30 people are needed.
(3) Now the number of watches per person is 1.5, so now the number of watches per person is 60.
Suppose x people are needed now, because the total number remains the same.
So we get 40* 18=60*X, and X= 12, so we subtract 18- 12=6 (person).